Hochland production plant in Sovata, Romania

Construction site: Hochland production plant in Sovata, Romania

Investor: HOCHLAND Romania SRL

Implementation: II Q 2006 – IV Q 2006

Scope of works (V.2006 – VI.2006):
Installation of 5-pole LV switchgear, capacitor batteries, own purpose switching station, execution of connections between LV switching station and transformers using 2 500 A bus-bridge, cabling cables supplying evaporator, lighting, 3-phase and socket installation, execution of cable routes, lightning arrester installation and potential compensation installation.

Scope of works (XII 2006):
Execution of external lighting installation on production and technological buildings elevation, execution of parking lighting installation, execution of installation supplying parking and plant entry gates.