Polonia Stadium in Warsaw
Construction site: Polonia Stadium in Warsaw
Investor: Association for the Rehabilitation of Polonia Stadium in Warsaw
Implementation: III Q 2003 - IV Q 2003 References
Scope of the works:
high and low current services including the replacement of the lighting fittings and wiring on the four masts, lighting control units for the mast stations, power supply terminal connectors, and remote wired control panel, as well as the removal of the old systems, an upgrade of the low voltage switchgear at two stations including the measurement system and automatic back-up power activation, plus the replacement of the low voltage mains cabling of the mast lighting.